NA - US - Chicago routing issues - workload taken out of production while routing issues are being investigated
Components affected
HiperZ USA - Chicago
Latest Updates ( sorted recent to last )
RESOLVED 3 months ago - at 01/24/2024 11:17AM

This incident has been resolved.

MONITORING 4 months ago - at 01/15/2024 10:12PM

Equinix IBX Site Staff reports that the site is still recovering and the average site temperatures have reduced an additional 2 degrees since the last update to 85° F. IBX Critical Facility Engineers along with onsite mechanical vendors continue working to restore the 5th Chiller. Note that temperatures may vary at different locations across the site. Fourteen portable coolers are online and the final portable cooler install is pending electrical wiring. For customers who powered down equipment, we strongly recommend waiting to restore operations until the average site temperatures reach around 80 °F

MONITORING 4 months ago - at 01/15/2024 04:30PM

Equinix IBX Site Staff reports that one of the mechanical vendors arrived on site to assist in troubleshooting and repair. Another mechanical vendor is en route to the IBX. The site is still recovering and the average temperature remains stable at 91° F. Thirteen portable coolers are online and two more continue to be installed. For customers who powered down equipment, we strongly recommend waiting to restore operations until the temperatures reach a lower overall range.

Our whole Chicago workload is still fully online and working properly, only peering and routings were affected.
We will keep this incident open as we are still at risk of failures until full cooling capacity at equinix is restored.

MONITORING 4 months ago - at 01/15/2024 12:46PM

Equinix IBX Site Staff reports that colocation temperatures continue to decrease slowly with a current average temperature at 85F degrees. Twelve portable coolers are now online and three more are being installed. For customers who powered down equipment, we strongly recommend waiting to restore operations until the temperatures reach a lower overall range.

MONITORING 4 months ago - at 01/15/2024 08:46AM

Equinix IBX Site Staff reports that colocation temperatures continue to remain stable with a current average temperature remaining at 95F degrees. Four portable coolers are now online and eleven more are being installed. For customers who powered down equipment, we strongly recommend waiting to restore operations until the temperatures reach a lower overall range.

MONITORING 4 months ago - at 01/15/2024 05:26AM

A fix has been implemented and we are monitoring the results.

IDENTIFIED 4 months ago - at 01/15/2024 03:28AM

Equinix IBX Site Staff reports that temperatures have stabilized with an average temperature of 120 F degrees. One chiller is now fully operational, and another chiller is online but operating at reduced capacity. Equinix IBX Critical Facility Engineers continue to work on restoring the required 4-out-of-6 chillers to return cooling back to normal operations. Portable chillers are currently enroute with an estimated arrival time of 21:00 Site Local Time. Upon arrival, IBX Critical Facility Engineers and our vendor partner will work diligently to get the portable chillers online as quickly as possible. We will send another update once the portable chillers are operational.

If not already implemented, Equinix site staff highly recommends that customers power down non-essential loads within the data center and/or transfer those operations to backup sites to assist with efforts at lowering the temperature within the facility.

The severe weather in the Chicago area, contributing to the initial failure, continues to hamper efforts at resolution, but our teams are working diligently to resolve the issue as quickly as possible. IBX Critical Facility Engineers continue to supply outside air to decrease the collocation area's temperature, and all fans have been deployed to support cooling the IBX.

IDENTIFIED 4 months ago - at 01/15/2024 02:46AM

The routing issues in Chicago are due overheating issues in Equinix CHI1.

Latest update from Equinix: Equinix engineers are still working with the vendor to rectify the fault
Latest update from Zayo: Our facility provider at 350 E Cermak has advised their chillers have stopped due to extreme outdoor temperatures. Our vendor has HVAC repair techs onsite and is working to get the units back in operation at this time. The unit failures is causing high temps on our equipment causing failure and flaps. We are working with them now to try to restore temperatures and then equipment. We will update as progress is made.

INVESTIGATING 4 months ago - at 01/15/2024 02:30AM

NA - US - Chicago routing issues - workload taken out of production while routing issues are being investigated

The easiest way to monitor HiperZ and all cloud vendors

With IsDown, you can monitor all your critical services' official status pages from one centralized dashboard and receive instant alerts the moment an outage is detected. Say goodbye to constantly checking multiple sites for updates and stay ahead of outages with IsDown.

Start free trial

No credit card required · Cancel anytime · 3154 services available

Integrations with Slack Microsoft Teams Google Chat Datadog PagerDuty Zapier Discord Webhook

Setup in 5 minutes or less

How much time you'll save your team, by having the outages information close to them?

14-day free trial · No credit card required · Cancel anytime